700 W Waterline Project

Share 700 W Waterline Project on Facebook Share 700 W Waterline Project on Twitter Share 700 W Waterline Project on Linkedin Email 700 W Waterline Project link

Consultation has concluded

The 700 W Waterline Project is a crucial infrastructure development undertaken by Midvale City to improve the existing infrastructure and secure a sustainable water supply for the long term. While the project is underway, there will be temporary inconveniences such as one-way road closures and traffic disruptions. However, we are dedicated to minimizing disruptions and ensuring that residents receive the necessary support and information throughout the project.

Project Duration

July 25, 2023, through October 2023



Location

The waterline project will take place on 700 W, stretching between Winchester Street and 6960 S. Construction work will begin on July 25 at the intersection of Winchester and 700 W, and will progress southward along 700 W.



Traffic Control and Detours

For the safety of the general public and the construction team, traffic control measures and detours will be in place throughout the project. Please follow the designated routes and respect any instructions from the traffic control personnel. Variable Message Signs will be strategically placed to provide you with important updates and guidance regarding traffic flow and alternative routes. It is vital for residents to refrain from parking vehicles on 700 West during the construction period. 


Updates

Updates are available below under the News Feed. For accurate and up-to-date information about the project and its impact on traffic, updates, and any necessary adjustments made to the project schedule be sure to subscribe to Project Updates under the Stay Informed icon



Questions?

If you have any questions related to the project, its timeline, or its impact on your daily life, we encourage you to submit a question below under the "Questions" tab. You can also contact Nolan and Son Construction Co., Inc. using the following numbers:
Office: 801-566-7219
Superintendent – Craig Necaise: 801-718-7964
24 Hr. Contact – Daniel Hill: 801-718-7984

We appreciate your cooperation and understanding as we work towards enhancing the water infrastructure in your area. Your support is vital in ensuring the success of this essential project.

The 700 W Waterline Project is a crucial infrastructure development undertaken by Midvale City to improve the existing infrastructure and secure a sustainable water supply for the long term. While the project is underway, there will be temporary inconveniences such as one-way road closures and traffic disruptions. However, we are dedicated to minimizing disruptions and ensuring that residents receive the necessary support and information throughout the project.

Project Duration

July 25, 2023, through October 2023



Location

The waterline project will take place on 700 W, stretching between Winchester Street and 6960 S. Construction work will begin on July 25 at the intersection of Winchester and 700 W, and will progress southward along 700 W.



Traffic Control and Detours

For the safety of the general public and the construction team, traffic control measures and detours will be in place throughout the project. Please follow the designated routes and respect any instructions from the traffic control personnel. Variable Message Signs will be strategically placed to provide you with important updates and guidance regarding traffic flow and alternative routes. It is vital for residents to refrain from parking vehicles on 700 West during the construction period. 


Updates

Updates are available below under the News Feed. For accurate and up-to-date information about the project and its impact on traffic, updates, and any necessary adjustments made to the project schedule be sure to subscribe to Project Updates under the Stay Informed icon



Questions?

If you have any questions related to the project, its timeline, or its impact on your daily life, we encourage you to submit a question below under the "Questions" tab. You can also contact Nolan and Son Construction Co., Inc. using the following numbers:
Office: 801-566-7219
Superintendent – Craig Necaise: 801-718-7964
24 Hr. Contact – Daniel Hill: 801-718-7984

We appreciate your cooperation and understanding as we work towards enhancing the water infrastructure in your area. Your support is vital in ensuring the success of this essential project.

Consultation has concluded
  • Progress Updates as of August 18, 2023

    Share Progress Updates as of August 18, 2023 on Facebook Share Progress Updates as of August 18, 2023 on Twitter Share Progress Updates as of August 18, 2023 on Linkedin Email Progress Updates as of August 18, 2023 link
    CLOSED: This discussion has concluded.

    Starting Friday, August 18, 2023, we'll be making some changes to the traffic flow to keep things moving smoothly as construction progresses. Here's what you need to know:

    • The northbound closure at 700 W and 6600 S will be REMOVED on Friday, August 18! That means you'll have full access to northbound lanes again, hooray!
    • To help keep traffic flowing smoothly during this phase, we'll be using Mobile Traffic Signal Devices starting on August 18. These devices will be controlling traffic as we move forward with the construction process.
    • This method of traffic control will be in place for the next 3 weeks as we work our way south with the construction progress.

    We know that these changes can be an adjustment, but we're committed to making this as seamless as possible. We appreciate your patience and understanding as we work to improve our infrastructure. Stay tuned for more updates and thank you for your cooperation during this important project.


  • Progress Update as of August 2, 2023

    Share Progress Update as of August 2, 2023 on Facebook Share Progress Update as of August 2, 2023 on Twitter Share Progress Update as of August 2, 2023 on Linkedin Email Progress Update as of August 2, 2023 link
    CLOSED: This discussion has concluded.
    • Work on Winchester Street will be completed this weekend, and normal traffic flow will be restored for eastbound travelers on Monday, August 7.

    • Northbound travel along 700 W will be restricted for the next 2 weeks. This road closure begins at 6600 W.

      • Detour Routes: 1300 W, I-15, 300 W, and State Street can be used as alternate routes to get around this construction closure.

    • 2 week outlook:

      • Construction will continue to progress south along 700 W from Winchester Street to 6600 S.


  • Phase 1: July 25, 2023 (Approximately 1 week) Eastbound Closure of Winchester @ 700 W

    Share Phase 1: July 25, 2023 (Approximately 1 week) Eastbound Closure of Winchester @ 700 W on Facebook Share Phase 1: July 25, 2023 (Approximately 1 week) Eastbound Closure of Winchester @ 700 W on Twitter Share Phase 1: July 25, 2023 (Approximately 1 week) Eastbound Closure of Winchester @ 700 W on Linkedin Email Phase 1: July 25, 2023 (Approximately 1 week) Eastbound Closure of Winchester @ 700 W link
    CLOSED: This discussion has concluded.


  • Respecting Detours: A Key to Smooth Waterline Project Implementation

    Share Respecting Detours: A Key to Smooth Waterline Project Implementation on Facebook Share Respecting Detours: A Key to Smooth Waterline Project Implementation on Twitter Share Respecting Detours: A Key to Smooth Waterline Project Implementation on Linkedin Email Respecting Detours: A Key to Smooth Waterline Project Implementation link
    CLOSED: This discussion has concluded.

    Waterline projects play a vital role in improving infrastructure and ensuring a reliable water supply for our communities. These projects often involve temporary road closures, detours, and restricted access to certain areas. As responsible drivers, it is important for us to understand and respect these necessary measures to ensure the smooth implementation of such projects. In this article, we emphasize the importance of driver cooperation and urge everyone to adhere to detours while avoiding areas designated for residents only.

    1. Safety First:
      • One of the primary reasons for implementing detours during waterline projects is to ensure the safety of both drivers and construction workers. Construction zones can present hazardous conditions, including uneven surfaces, heavy machinery, and restricted visibility. By following designated detours, drivers minimize the risk of accidents and contribute to a safer work environment.
    1. Efficient Progress:
      • Detours are carefully planned to facilitate the efficient progress of waterline projects. They help redirect traffic away from construction zones, allowing construction crews to work without unnecessary disruptions. By respecting detours, drivers contribute to a smoother flow of traffic and help expedite the completion of the project, minimizing inconveniences in the long run.
    1. Residents-Only Areas:
      • In some cases, certain areas affected by the waterline project may be designated for residents only. These areas often include residential streets and neighborhoods directly impacted by construction activities. It is essential for drivers to honor these restrictions and avoid entering these zones unless they are residents or have explicit permission. Respecting these restrictions demonstrates consideration for the residents' privacy and safety during this temporary phase.
    1. Follow Signage and Instructions:
      • Detours and restricted areas are clearly marked with signage and instructions to guide drivers along alternative routes. It is crucial to pay attention to these signs and follow the provided directions. Disregarding signage not only puts drivers at risk but can also hinder the progress of the waterline project. By following instructions, drivers ensure a smooth flow of traffic and contribute to the overall success of the project.
    1. Patience and Understanding:
      • Waterline projects are vital for the long-term improvement of our infrastructure and the provision of a reliable water supply. It is important for drivers to approach these projects with patience and understanding. Temporary inconveniences, such as detours and restricted areas, may disrupt our usual travel routes, but they are necessary for the greater benefit of the community. By exhibiting patience and understanding, we can help create a positive environment for everyone involved.

    By prioritizing safety, following signage and instructions, and demonstrating patience and understanding, we contribute to the efficient progress of the project while minimizing disruptions. Let us work together to ensure the smooth execution of waterline projects and the improvement of our infrastructure for the benefit of all.